In short
- Land is in-plan (inside an approved town plan), in a settlement, or out-of-plan. Each has its own building rules.
- Out of plan, the general rule is a minimum of 4,000 m² with 25 m of frontage on a public road.
- The Council of State ruled in 2023 that the road must be a lawful public road. Which roads count is still being settled.
- Smaller older plots (750, 1,200 or 2,000 m²) can only be built on if the owner applied by 9 December 2022, and the permit window runs to 30 June 2027.
- Local spatial plans can change what is allowed, so check the plan that applies to the plot.
Three categories of land
- In-plan (εντός σχεδίου): land inside an approved town plan, with its own building terms such as coverage, building coefficient and height.
- Settlements (οικισμοί): legally existing pre-1923 settlements, or settlements under 2,000 inhabitants with official boundaries. A 2025 decree set new criteria for these boundaries, and some will be redrawn when local plans are prepared.
- Out-of-plan (εκτός σχεδίου): everything else. Building here is the exception and depends on plot size and road access.
The planning rules were gathered into a new Spatial Planning and Urban Planning Code, ratified by Law 5306/2026 in June 2026.
The out-of-plan rules
Under the 1985 decree now carried into the Code, an out-of-plan plot is buildable as a rule (κατά κανόνα άρτιο) with at least 4,000 m² and 25 m of frontage on a public road (κοινόχρηστος δρόμος). Stricter figures apply along major roads.
In its Plenary decision 176/2023, the Council of State held that area alone is not enough: the plot must front a lawfully existing public road that was not created by private will. A Presidential Decree on how out-of-plan roads are recognised is still pending, and building offices have applied the rules inconsistently in the meantime.
A track to the plot, even one used for decades, may not count as a public road. Ask your engineer what evidence shows the road's status before you rely on it.
Smaller, older plots
Plots created before certain dates could be built on with less area, by exception (κατά παρέκκλιση): 750 m² with 10 m frontage, 1,200 m² with 20 m, or 2,000 m² with 25 m, depending on when the plot was created and the road it fronts.
Law 4759/2020 ended these exceptions with a transition period. Only owners who applied for a pre-approval or a confirmation of building terms by 9 December 2022 can still use them, and, according to the Technical Chamber of Greece, the permit must be issued by 30 June 2027 after the latest extension. This deadline has been extended several times, so check it with your engineer. Once a new local plan is approved for the area, the exception regime ends there.
If a seller describes a small out-of-plan plot as buildable, ask to see the 2022 filing and check the dates. Without it, the plot may not be buildable at all.
Local spatial plans
Local Urban Plans (ΤΠΣ) are replacing the older General Urban Plans (ΓΠΣ) and plans for open-land areas (ΣΧΟΟΑΠ). Special Urban Plans (ΕΠΣ) sit at the same level and can override them. A new plan can change land uses and building terms, and can also end the small-plot exceptions described above.
Forest, Natura 2000, coastal and archaeological rules can apply on top of all of this, so a plot that meets the size and road rules can still be restricted.
What a public-data pre-check shows
The report confirms the cadastral parcel and its mapped area, and checks it against forest maps, flood zones and Natura 2000. The Extended report adds land cover, settlement context and distance to the nearest mapped road, all from public data. That shows early whether an out-of-plan plot has obvious obstacles.
What it cannot tell you
It does not decide whether a plot is buildable. It cannot tell you the planning category, whether a road is a lawful public road, whether a 2022 filing exists, or which local plan applies. Your engineer confirms these with the building office.
See a sample report →Questions for your lawyer or engineer
- 01Is this plot in-plan, in a settlement, or out-of-plan, and which local plan applies? Is a new one being prepared?
- 02Is it buildable as a rule (4,000 m² and 25 m frontage) or only by exception?
- 03If by exception, was a pre-approval or confirmation filed by 9 December 2022, and can a permit be issued by 30 June 2027?
- 04Does the frontage road count as a lawful public road, and what evidence shows it?
- 05Can you obtain a written confirmation of building terms, or of the plot's size and buildability, from the building office?
- 06Do forest, Natura, coastal or archaeological rules also apply?
Greek terms
| Greek | English | Meaning |
|---|---|---|
| Εντός σχεδίου | In-plan | Inside an approved town plan. |
| Εκτός σχεδίου | Out-of-plan | Outside any town plan or settlement. |
| Οικισμός | Settlement | Pre-1923 or under-2,000 settlement with official boundaries. |
| Αρτιότητα | Minimum plot rules | Minimum area and frontage needed to build. |
| Κατά παρέκκλιση άρτιο | Buildable by exception | Older smaller plots allowed under transition rules. |
| Κοινόχρηστος δρόμος | Public road | Road that counts for frontage; must exist lawfully. |
| Βεβαίωση όρων δόμησης | Confirmation of building terms | Building office confirmation of what can be built. |
| ΤΠΣ / ΕΠΣ | Local / Special Urban Plan | Binding local plans that set land uses. |